Buderim Landscaping – Day 13
Day 13 – Wednesday 29th November
At 3pm on Tuesday the rain came in and saturated the site. It rained heavily for at least 2 hours. Hence, we woke to a very soggy work site this morning. The boys persisted and bailed out the water from the post holes and continued with the aligning and concreting the supports into place.






The post holes for the pool deck supports

Timber for the deck support was delivered today.


Another storm brewing, but this time it went around us.